Mirage @ Manhattan · Bid fill (code + plans checked)

100′×110′×5 · 55,000 SF · 56 keys · H=64′ · O1/O2 · RC III · WBDR shutters in Div 08 · pool $70k · wellness $0

WORKING HARD: $3,400,000  ·  OWNER MAX HARD: $3,800,000
LAND: $435,000  →  ALL-IN WORKING ~$3,835,000  ·  ALL-IN MAX ~$4,235,000
Soft DOWN $20k — IFC pack already done (PE design cut). AHJ fees still real. Pool $70k · land $435k.
Checked vs drawings: A1.0–A1.4 · A2.0/A2.1 · ADA1.0 · C0.0 H-1 · G0.1 · K1.0 · S0.1 · CFS BOQ
Geometry MATCH · 56 keys MATCH · O1/O2 MATCH · pool A2.1 MATCH · parking 100 MATCH · wellness absent MATCH
Land $435k · Headroom to max $380k · Matrix: 00-CALCS/PLAN-vs-BID-CHECK.txt
Drawing fixes before seal (not bid-ups): A2 notes still say WBDR “ALT” → change to BASE (impact OR shutters) per G0.1. ADA1.0 shows 4 mobility keys vs calcs “2 Type A” → AOR reconcile; bid TI follows plans (4).

A · Hard SOV (last bid lines · pool corrected · land $435k)

DivScopeBasisLean $Working $Bid $
01General · lean OH&P · insuranceLast bid70,00095,000
02/31Site pad · grading · util lateralsLast bid40,00055,000
32Parking 100 · asphalt · ADA · loading · landscapeH-1 plans135,000175,000
03Foundations · SOG · elev pit · no piles*Geotech confirm shallow150,000165,000
05CFS dried-in · wind 160 Exp CCFS BOQ · RFQ ≤$1.0M1,000,0001,150,000
07Roof · WRB · insulation · crownLast bid90,000110,000
08Openings + WBDR shutters + F-FRONTSame $ as last 08+F — WBDR in base115,000140,000
09-L1L1 Mirage + CRAVE TI (FFE NIC)Last bid185,000210,000
09-Keys56 unit TI + corridorsLast bid480,000500,000
06Wellness / chairsNot in program000
14Elevator 5-stopLast bid80,00095,000
21NFPA 13 + standpipeLast bid107,000120,000
22/23/26P / HVAC / E / FA / greaseLast bid lean MEP193,000205,000
PoolNorth court pool$70k (was $110/$125)70,00070,000
SoftPE seal/gaps · AHJ fees · geotech · SI · BRSplit below — pack credit118,000160,000
Cont.ContingencyLast bid100,000150,000
GC HARD TOTAL2,933,0003,400,000
Land (separate)435,000435,000435,000
ALL-IN3,368,0003,835,000
OWNER HARD MAX / ALL-IN MAXHard ≤ $3,800,000 · All-in ≤ ~$4,235,000

Soft split (why not still $180k)

ItemWhyLean $Working $
PE seal / gap-close (family)IFC-3.2 drawings+calcs already built — not full CD from scratch25,00035,000
AHJ fees (JP + OSFM + LDH + Planning)Parish/state fees on valuation — our pack does not reduce these25,00035,000
Geotech reportStill required (attach gate)15,00020,000
COMcheck + Hazard Tool + filingsSoftware / prints3,0005,000
Testing / special inspectionsIBC Ch.17 during build30,00040,000
Builder’s riskDuring construction20,00025,000
SOFT TOTAL (was $140k / $180k)118,000160,000

* Foundations assume shallow — geotech confirms. CFS RFQ ≤$1.0M · wellness $0. Permit fees ≠ design fees. Work we did cuts PE design; AHJ still charges.