MIRAGE 1705 · TAKEOFF + FRAMING TRUTH ==================================== Date: Jul 20, 2026 · after independent CAD remasure (geometry.py plate) Status: REVIEWER WAS RIGHT — prior BOQ / triple-check were partly self-referential VERDICT ------- Envelope SF (gross/net/openings) was OK. Joist LF, unit SF, interior partition LF, and framing language were OFF or schematic. Member sizes in walls_CFS / floors_CFS remain PRELIMINARY — EOR seals fab, not this pack. 1. UNIT SF — OFF (−520 SF / −1.4%) --------------------------------- Program claim (marketing): 48×610 + 8×850 = 36,080 SF CAD plate (truth): 8,890 SF/floor × 4 = 35,560 SF Root cause — pack is 30'+6'+30'+6'+28' (east band only 28' wide): West/mid 30' band: 30×20'-4" = 610 · 30×28'-4" = 850 (true) East 28' band: 28×20'-4" = 569 · 28×28'-4" = 793 (labeled 610/850 — FALSE) Remnant stretch: 204 ≈ 620 · 209 ≈ 680 · 214 ≈ 579 USE 35,560 SF for area / load / takeoff. Keep 610/850 as SKU labels only until plate re-packs. 2. FLOOR JOISTS — OFF (+636 LF/floor / +8%) ------------------------------------------ Old BOQ: 7,890 LF/floor = plate area method (11,000 ÷ 1.333 × 0.956) CAD remasure @16" o.c. with correct span by bay: Units + core + link: joists span N-S (unit depth 20'-4" / 28'-4") Halls H1/H2: joists span E-W (6' corridor width) L2 total = 8,526 LF · L3–L5 same plate = 8,526 each L2–L5 total = 34,104 LF (was 31,560) Old note “span short N-S / run E-W” mixed orientation language. Locked rule for fab (EOR confirm): · Guest/core bays → span short N-S between E-W bearing/demising walls · N-S corridors → span short E-W across 6' hall · Do NOT run 110' joists the full plate depth 3. INTERIOR CORRIDOR + DEMISING — WAS ORDER-OF-MAG ------------------------------------------------- Old BOQ: 870 LF/floor (hand estimate) CAD stack demising (W+mid+E): 382 LF Corridor long walls (2 halls × 2 × 110'): 440 LF CAD subtotal: 822 LF/floor (−48 vs old) Wet-wall / bath partitions: NOT in CAD plate — ALLOWANCE 168 LF/floor (12 LF × 14 keys) If wet walls in same line: 822 + 168 = 990 LF/floor (ALLOWANCE) 4. EXT STUDS — OK (keep 314) ---------------------------- 420' perimeter @16" with corner share = 314 pcs/floor (not 315). Track 840 LF/floor OK. Gross/net wall SF OK. 5. OPENING PACK A.6 2,460 LF — STILL ALLOWANCE --------------------------------------------- Not CAD-remeasured from window/door schedule. Do not fab from this line. 6. FRAMING MEMBER SIZES — SCHEMATIC ---------------------------------- walls_CFS / floors_CFS marks (800S200-97, 1000S162-54, 1400S162-68, etc.) are criteria / eng_calcs preliminary with OK interaction ratios. They are NOT a sealed fab BOM. EOR must lock stud/joist/track before shop drawings. ACTION LOCKED IN THIS REVISION ------------------------------ ✓ BOQ joist LF → 8,526/floor ✓ BOQ interior → 822 CAD + wet allowance called out ✓ This truth sheet + QTO / triple-check updated ✓ geometry Room.sf → CAD w×d (stops lying 610 on 569 rooms) □ Plate re-pack if owner requires every key to be true 610/850 (needs AOR) □ EOR seal joist orientation + member schedule before fab □ Opening pack remasure from sealed A2 schedule