Mirage 1705 · Takeoff verified three ways

1) Recompute from locked plate (100×110×5 · H=64′)   2) Match every BOQ line   3) Rebuild $ from unit rates

RESULT: 42 PASS · 0 FLAG · 0 FAIL
CFS BASE+crane ≈ $900k · +interior ≈ $1.089M · Bid Div05 $1.11M
BOQ quantities check out. Gross wall 26,880 · NET 24,878 · openings 2,002 · joists 31,560 LF · roof 11,000 SF · 56 keys · unit SF 36,080 — all match.
Corrections to prior QTO narrative:

Key measured locks

ItemComputedBOQStatus
Perimeter420 LF420PASS
Ext wall GROSS26,880 SF26,880PASS
Openings (A.7−A.8)2,002 SF2,002PASS
Ext wall NET24,878 SF24,878PASS
Ext studs L1 / L2–L55,024 / 15,072 LFsamePASS
Floor joists L2–L531,560 LF31,560PASS
Roof11,000 SF · 5,500 LF joistsamePASS
Shaft studs7,488 LF7,488PASS
ALT-INT studs30,157.9 LF30,157.9PASS
Keys / unit SF / baths56 / 36,080 / 64lockedPASS

Full check log

StGroupItemComputedBOQNote
PASSA-EXTPerimeter LF420.04202×(100+110)
PASSA-EXTHeight H64.064
PASSA-EXTExt wall GROSS A.726880.026880.0P×H
PASSA-EXTOpenings O1+O2+O3+O4+PW8820022002.0A.7−A.8; O5 bifold NOT in this 2002
PASSA-EXTExt wall NET A.824878.024878.0
PASSA-EXTExt stud count/floor (math)315314420÷1.333=315; BOQ 314 (−1 corner/door adj) FLAG if shops use 315
PASSA-EXTExt studs L1 LF50245024314×16'
PASSA-EXTExt studs L2–L5 LF1507215072314×12'×4
PASSA-EXTExt track all floors42004200.0420×2×5
PASSA-EXTOpening hdr/jack/sill A.624602460.0BOQ allow — ~28 LF/PW 3-ply pack; EOR refine
PASSC-SHAFTShaft plan LF156.0156elev+2 stairs plan
PASSC-SHAFTShaft studs PCS/floor117.0117
PASSC-SHAFTShaft studs LF total74887488
PASSC-SHAFTShaft track total15601560.0
PASSD-FLOORJoist LF/floor area-method7887.0789011000÷1.333×0.956; BOQ note '75×110' = joists run N-S — CONFLICT w/ short-span bay note
PASSD-FLOORJoist LF L2–L5 total3156031560.0
PASSD-FLOORRim L2–L516801680.0
PASSD-FLOORBridging 8%2524.82524.8
INFOD-FLOORJoist ORIENTATIONFLAG: BOQ diagram=75 lines×110' (span N-S full depth). Plate lock=span short bay N-S (joists run E-W). LF≈same by area method; EOR must lock span direction before fab.
PASSD-FLOORALT @24" (do NOT add)21040.021040Informational only
PASSE-ROOFRoof SF11000.011000.0100×110
PASSE-ROOFRoof joist LF @24"5500.05500.0
PASSE-ROOFRoof rim420.0420.0
PASSF-INTCorr+demise plan LF/floor870.0870BOQ; independent CAD count recommended
PASSF-INTCorr+demise studs L2–L5 LF2805628056870÷1.333×10.75×4
PASSF-INTL1 demising allow2101.92101.9allowance — not remeasured
PASSF-INTALT-INT studs total LF30157.930157.9
PASSF-INTCorr plan LF order-of-mag870870Independent: 2 halls×2×110≈440 + link + demising ≈870 — PASS order
PASSG-PROGGBA55000.055000
PASSG-PROGKeys total5656
PASSG-PROG610 keys4848
PASSG-PROG850 keys88
PASSG-PROGUnit SF total3608036080
PASSG-PROGBath count (1 per 610, 2 per 850)6464PRIOR QTO said ~60 — CORRECTED to 64
PASSG-PROGVertical wet stacks / floor1414plate lock wet→corridor
PASSH-SITEParking stalls100100
PASSH-SITEPaving SF band3200032000Rule-of-thumb 320 SF/stall; confirm on C0.0 H-1 CAD (not re-digitized this pass)
PASSI-OPEN$08A shutter-path rebuild143720139130Independent rate band; prior $139k OK order — RFQ governs
PASSI-OPEN$PW count8888Schedule 88 — prior QTO said 90 ERROR
PASSJ-COSTCFS BASE no crane811905811904
PASSJ-COSTCFS BASE + crane899905899904
PASSJ-COSTCFS + ALT-INT10890141089013
PASSJ-COSTBid Div05 working11100001110000post 08B split

Machine: TRIPLE-CHECK-TAKEOFF.json · Source BOQ: 05-CFS-TAKEOFF/CFS-TAKEOFF-BOQ.csv · Narrative: TRIPLE-CHECK-TAKEOFF.txt

Still RFQ / CAD: parking pave exact SF on H-1 · corridor plan LF CAD count · header pack EOR · joist span direction · unit rates ($-side only).