CD-ready owner lock · Jul 2026

Verify & stamp.
Do not redesign.

Owner has locked plate, 56 keys, demising, unit modules, and door/window/finish schedules so AOR/PE work is code verification + sealed CAD/BIM — not inventing a new building. Contractors build only from LA-sealed CDs. HTML is the coordination lock. Zero LA-stamped sheets until professionals seal.

0LA-stamped sheets
CD-readyOwner lock + schedules
56residence keys locked
100%Target @ AOR seal

Engagement language: “Owner program is LOCKED. Do not redesign plate, key count, demising, or unit modules. Scope = code compliance verification, detailing, discipline coordination, sealed permit CDs, Jefferson submittal support. Variations only with written owner change order.” Full schedules: CD-ready handoff →

Two questions · two answers

Is the concept good? Yes

Destination-first · A-2 restaurant + accessory courtyard principal · hotel/retail supporting. Easier to permit and finance than “entertainment resort.” Pre-app asks for staff conference first — appropriate.

Will Planning approve? Nobody can promise yes

Packet is moving the right direction: simplified narrative, parking worksheet, flood desktop, circulation. Staff still reviews zoning · access · life safety · stormwater · utilities · landscaping · traffic.

Will AOR/PE stamp owner HTML? No — they stamp their CAD

They convert the locked program into sealed CDs. Engagement = verify & stamp, not redesign 56 keys / plate.

Can PEMB vendor quote? Yes

Footprint · stories · eave · openings · roll-ups · hotel layout · court void · frame grid — enough for preliminary proposal, then refine after PE.

Can GC bid? Yes · from stamp package

Full drawing set at aor-transfer.html — DXF, plans, parking, kitchen.

Stamp path Due diligence → stamp

Package is ready. Architect / engineer completes DD and stamps.

Owner lock · Day 1 full program

Full program · stamp after due diligence.

Drawing package is complete. Path below is the due-diligence checklist before stamp for Jefferson MU-CD.

DisciplineIn packageStamp after DD
Structural / PEMBFrame grid · anchor concept · wind note placeholderFoundation design · anchor bolts · steel sizing · uplift · hurricane · lateral bracing · PEMB shop drawings
CivilSurvey sketch on PLS #8387 · parking count worksheetGrading · drainage · detention · utilities · ADA slopes · FFE · stamped ALTA verification
MechanicalCoordination sheet · hood length note · hotel shaft conceptHVAC calcs · kitchen exhaust · makeup air · smoke control · hotel ventilation
PlumbingFixture counts schematic · grease interceptor location noteWater/sanitary sizing · GI sizing · hot water · health dept coordination
ElectricalService location concept · court lighting intentLoad calcs · service sizing · emergency · fire alarm · photometric if required
Fire protectionNFPA 13 zone concept · occupancy labelsSprinkler calcs · rated separations · exits · travel distance · Fire Marshal submittal
Architect / codeMixed-use diagram · A-2 + hotel + retail labelsMixed occupancy analysis · accessibility · energy · life safety · door/window schedules · specs · finishes

Gap list · before permit submittal

What is still missing for stamped permit submittal.

ItemStatusCloses with
Geotechnical reportGapLA geotech · slab/spread footings @ Zone X bowl
ALTA survey · certifiedGapSurveyor · verify PLS #8387 · easements · FFE
Civil engineering · drainage/detentionP3 schematicLA civil PE · seal P3-C0-1
Structural · PEMB shop drawingsCoord onlyPEMB vendor + LA PE seal
Full MEP engineeringP3 preliminaryMEP engineer of record · seal P3-M0/M1/M2
Fire protection engineeringP3 preliminaryFPE seal P3-FP1.1 · Fire Marshal
Door · window · hardware schedulesSchematicAOR permit set
Waterproofing · roofing detailsGapAOR + PEMB vendor
Kitchen equipment shop drawingsGapFood service consultant + Health
Reflected ceiling · lighting plansGapAOR · exposed deck rule documented
Material + finish specificationsOwner lockAOR spec book
ADA details · routes · parkingGapAOR + civil
Construction specifications (CSI)GapAOR
Energy code documentationGapAOR / COMcheck
Jefferson written pre-app OK · items 1–3 + E1PendingPlanning staff conference
MAI appraisal · as-complete w/ keysGapIndependent @ land close

Recommended sequence

Path to stamped permit set

  1. Jefferson pre-application conference — written direction on principal use · parking · access · court accessory · 48-key supporting
  2. Geotech + ALTA — foundation type · FFE · easements · detention envelope
  3. Engage LA AOR + civil PE + MEP/FP — contract on owner lock geometry · 55,000 SF GBA · program schedule
  4. PEMB vendor preliminary → PE-stamped shop — frame · connections · anchor bolts
  5. Schematic Design (SD) sign-off — mixed occupancy · egress · kitchen health path
  6. Design Development (DD) — MEP sized · sprinkler · electrical service · civil grading
  7. Construction Documents (CD) 100% — every sheet in checklist above · AOR seal
  8. Building permit submittal — Jefferson + State Fire Marshal + LDH food if required
  9. Stamped GC lump-sum — after permit-ready set · not before

Site program · square footage lock

Financial model and comps use 55,000 SF GBA footprint (PEMB 100′ × 110′) · 56 residence keys · 8,100 SF A-2. Full zone table: P&L program schedule → · homepage →