CFS / framing · CAD remasure Jul 20, 2026
Takeoff · corrected
Earlier BOQs were inaccurate (area-method joists, marketing unit SF).
This page is the CAD-corrected BOQ matched to geometry.py plate.
Use this file:
CFS-TAKEOFF-BOQ.csv
(also synced to
packet/build/).
Read truth notes before fab.
Ignore: any older BOQ with joists 7,890 LF/floor or unit SF 36,080.
Also ignore the Jul 15 “full takeoff PDF” if it still shows those numbers — CSV below is authority.
What was wrong → what to use
| Item | Old (wrong) | CAD truth |
|---|---|---|
| Floor joists L2–L5 (each) | 7,890 LF | 8,526 LF |
| Joists L2–L5 total | 31,560 LF | 34,104 LF |
| Guest unit SF L2–L5 | 36,080 SF | 35,560 SF |
| Corr + demising / floor | ~870 LF | 822 LF CAD |
| Wet-wall / bath / floor | — | 168 LF allowance |
| Ext studs / floor | 314 pcs | 314 pcs (OK) |
| Opening pack A.6 | 2,460 LF | 2,460 LF allowance (not CAD) |
Unit labels stay 610/850 SKU — east 28′ band CAD SF is less (569 / 793). Use 35,560 SF for area/load/takeoff until plate re-packs. Joists: units/core span short N–S; halls span E–W across 6′ — not 110′ full-depth joists.
Downloads
★ CFS-TAKEOFF-BOQ.csvCorrected line items · BASE + ALT-INT + PROG.
★ Framing truthWhy old numbers failed · orientation lock.
Triple-checkPASS / FAIL → FIX log.
QTO auditHTML audit (if present).
Full blueprintsPlans this takeoff was measured from.
Quote package PDFVendor invite — use with corrected CSV.
BOQ on this page
| Phase | Code | Description | Qty | Unit | Floor | Note |
|---|---|---|---|---|---|---|
| Loading… | ||||||
Folder: professionals/aor-transfer/06-CFS-TAKEOFF/
· Local twin: 11-IFC-ACCURATE/12-AOR-PE-TRANSFER/04-CFS-BOQ/