CFS / framing · CAD remasure Jul 20, 2026

Takeoff · corrected

Earlier BOQs were inaccurate (area-method joists, marketing unit SF). This page is the CAD-corrected BOQ matched to geometry.py plate.

Use this file: CFS-TAKEOFF-BOQ.csv (also synced to packet/build/). Read truth notes before fab.
Ignore: any older BOQ with joists 7,890 LF/floor or unit SF 36,080. Also ignore the Jul 15 “full takeoff PDF” if it still shows those numbers — CSV below is authority.

What was wrong → what to use

ItemOld (wrong)CAD truth
Floor joists L2–L5 (each)7,890 LF8,526 LF
Joists L2–L5 total31,560 LF34,104 LF
Guest unit SF L2–L536,080 SF35,560 SF
Corr + demising / floor~870 LF822 LF CAD
Wet-wall / bath / floor168 LF allowance
Ext studs / floor314 pcs314 pcs (OK)
Opening pack A.62,460 LF2,460 LF allowance (not CAD)

Unit labels stay 610/850 SKU — east 28′ band CAD SF is less (569 / 793). Use 35,560 SF for area/load/takeoff until plate re-packs. Joists: units/core span short N–S; halls span E–W across 6′ — not 110′ full-depth joists.

Downloads

★ CFS-TAKEOFF-BOQ.csvCorrected line items · BASE + ALT-INT + PROG. ★ Framing truthWhy old numbers failed · orientation lock. Triple-checkPASS / FAIL → FIX log. QTO auditHTML audit (if present). Full blueprintsPlans this takeoff was measured from. Quote package PDFVendor invite — use with corrected CSV.

BOQ on this page

PhaseCodeDescriptionQtyUnitFloorNote
Loading…

Folder: professionals/aor-transfer/06-CFS-TAKEOFF/ · Local twin: 11-IFC-ACCURATE/12-AOR-PE-TRANSFER/04-CFS-BOQ/